Reported Date :
06-FEB-17
|
MOU Status :
Not Under MOU for 2015-2016
|
Monthly Report :
12
/
2016
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
64
|
Total/Pending/Completed Milestone -
6
/
0
/
6
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Detailed route survey completed. All obstacle crossing permission received. All major order placed and all material received at site.
Part-A (Vijaipur to Boreri section- 112 Km): Gas in done on 23.04.2013.
Part-C ( 72 Km) : Hydrotesting completed on 13.03.2016.Station work completed.
Part-D & E(97Km) :Lowering completed.
Hydrotest completed for Part-D and Part-E
Chambal HDD of 2320 mtr length ( in three part) Completed.
Hydrotest completed for Part-D & E. Re-hydrotest of already laid section of Part-E to ensure line pipe health & integrity completed in totality.
Terminal works completed.
Pipeline commissionied on 31.10.2016 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |