Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : VKPL UPGRADATION AND LAYING OF SPURLINE (TO BHILWARA AND CHITTORGARH).

Reported Date : 06-FEB-17

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 12 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    64

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
463.320463.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
356.643.5515.41415.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/201110/201610/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
730

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Detailed route survey completed. All obstacle crossing permission received. All major order placed and all material received at site. Part-A (Vijaipur to Boreri section- 112 Km): Gas in done on 23.04.2013. Part-C ( 72 Km) : Hydrotesting completed on 13.03.2016.Station work completed. Part-D & E(97Km) :Lowering completed. Hydrotest completed for Part-D and Part-E Chambal HDD of 2320 mtr length ( in three part) Completed. Hydrotest completed for Part-D & E. Re-hydrotest of already laid section of Part-E to ensure line pipe health & integrity completed in totality. Terminal works completed. Pipeline commissionied on 31.10.2016

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone