Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : DBNPL SPURLINE (UTTRANCHAL AND PUNJAB).

Reported Date : 05-DEC-14

MOU Status : Not Under MOU for 2014-2015

Monthly Report : 10 / 2014

Cost Overrun (%)-   0

Time Overrun (Months)-    40

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
540.920540.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
336.284.64.02340.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20110/010/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

PMC: Mecon Ph-1: Commissioned ( Ludhiana- Jalandhar Pipeline and Saharnpur-Haridwar Pipeline Project) Ph-II ( Haridwar-Rishikesh-Dehradun section): Currently no fresh activities are under taken as there is no consumers for this section. Proposal for closure of project activities has been put up to Board and approval awaited. However the above project may be revived in synchronization with consumers tie up and their readiness to draw gas.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone