Reported Date :
05-DEC-14
|
MOU Status :
Not Under MOU for 2014-2015
|
Monthly Report :
10
/
2014
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
40
|
Total/Pending/Completed Milestone -
7
/
0
/
7
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
PMC: Mecon
Ph-1: Commissioned ( Ludhiana- Jalandhar Pipeline and Saharnpur-Haridwar Pipeline Project)
Ph-II ( Haridwar-Rishikesh-Dehradun section):
Currently no fresh activities are under taken as there is no consumers for this section. Proposal for closure of project activities has been put up to Board and approval awaited. However the above project may be revived in synchronization with consumers tie up and their readiness to draw gas. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |