Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : NORTH TAPTI GAS FIELD DEVELOPMENT.

Reported Date : 12-SEP-13

Monthly Report : 7 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
589.7973.79973.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
729.51183.020912.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20115/20115/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1000

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-13100Completed

Monthly Status

Background Information

BOTH THE WELL PLATFORMS HAVE BEEN INSTALLED. DRILLING OF ALL 6 WELLS HAS BEEN COMPLETED. PROJECT HAS BEEN COMPLETED SUCCESSFULLY ON 13.05.13.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks