Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF WO-16 CLUSTER FIELDS.

Reported Date : 05-APR-16

Monthly Report : 2 / 2016

  

   

Total/Pending/Completed Milestone - 13 / 9 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
252325232523

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1019.76773.0901792.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/201412/20151/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
36.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-16100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks