Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : FLUIDIZED CATALYTIC CRACKING UNIT(FCCU) REVAMP AT MATHURA REFINERY.

Reported Date : 24-FEB-14

Monthly Report : 12 / 2013

  

   

Total/Pending/Completed Milestone - 18 / 0 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
100001000

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
455.45299.8141.2755.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20130/01/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2700

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks