Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : BUTADIENE EXTRACTION UNIT(BDEU) AT PANIPAT.

Reported Date : 21-NOV-13

MOU Status :

Monthly Report : 9 / 2013

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 42 / 0 / 42

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
341.50341.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
169.8622.886.07198.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20130/09/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
66.840

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone