Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : CHENNAI PETROLEUM CORPORATION LIMITED.
Project Name : EURO-IV DHDT.

Reported Date : 30-APR-13

Monthly Report : 2 / 2013

  

   

Total/Pending/Completed Milestone - 116 / 0 / 116

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2615.6902615.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1890.3690.6701981.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20100/01/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
180.62180.62

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-12100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks