Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : PETROCHEMICAL COMPLEX-II AT VIJAYPUR AND PATA.

Reported Date : 15-MAY-15

MOU Status : Not Under MOU for 2014-2015

Monthly Report : 3 / 2015

Cost Overrun (%)-   7.52

Time Overrun (Months)-    10

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
814008752

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6422.49845.521071.897494.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20140/012/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
12520

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.5Completed

Monthly Status

Background Information

Mechanical completion acheived on Dec 2014. The unit at Vijaipur was commissioned on 28 Mar 2015 and Pata polymer production and cracking from furncae started on 30 Mar 2015.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone