Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : MANGALORE REFINERY AND PETROCHEMICALS LIMITED.
Project Name : MRPL PHASE-III EXPANSION.

Reported Date : 02-DEC-14

Monthly Report : 10 / 2014

  

   

Total/Pending/Completed Milestone - 108 / 0 / 108

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
12412012160.26

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11332.93495.61377.212205.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20120/010/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5850

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.85Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks