Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CONSTRUCTION OF TANKS AND BLENDING FACILITY AT VADINAR.

Reported Date : 30-MAY-13

Monthly Report : 3 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2670267

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
195.0929.320224.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20120/03/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks