Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF SB-14 FIELD.

Reported Date : 12-MAY-14

Monthly Report : 3 / 2014

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
410.440410.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
210.5826.58100337.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20120/03/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
620

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-14100Completed

Monthly Status

Background Information

PROGRESS DURING THE MONTH IS 6.4%. PROJECT IS COMPLETE.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks