Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : 102 MW WIND POWER PROJECT.

Reported Date : 02-DEC-15

Monthly Report : 10 / 2015

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1106678.02678.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
40532.690437.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20123/20159/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-SEP-15100Completed