Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : INTEGRATED DEVELOPMENT OF B-127 FIELDS.

Reported Date : 22-JUN-20

Monthly Report : 4 / 2020

  

   

Total/Pending/Completed Milestone - 18 / 0 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2059.632665.652665.65

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2011.8002011.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20153/20203/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
145.3991

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-20100Completed

Monthly Status

Background Information

Project completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks