Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : FIRE WATER NETWORK AT URAN.

Reported Date : 09-SEP-14

Monthly Report : 7 / 2014

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
171.680121.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
96.43013.91110.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20130/07/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-14100Completed

Monthly Status

Background Information

PROJECT WAS COMPLETED SUCCESSFULLY ON 08.07.14.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks