Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : INTEGRATED REFINERY EXPANSION PROJECT.

Reported Date : 07-NOV-17

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 9 / 2017

Cost Overrun (%)-   0

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 16 / 1 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
16504016504

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
14729.61243.55117.8315090.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20170/09/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5310

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

All units / facilities in IREP are mechanically completed in March 2017 as per schedule and all units have been commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone