Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PARADIP HALDIA DURGAPUR LPG PIPELINE.

Reported Date : 07-FEB-19

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 12 / 2018

Cost Overrun (%)-   45.67

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
91313301330

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1200.16123.2.171323.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20180/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1160

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project mechanically completed in oct-2018. • Paradip-Balasore section (approximately 157 Km) with Balasore and Paradip station commissioned on 16.10.2017. • Balasore – Haldia section (approximately 189 Km) Commissioned on 18.12.2018. • Haldia –Durgapur section (approximately 269 Km) Commissioned on 6.12.2018. • The Project has been commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone