Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : MANGALORE REFINERY AND PETROCHEMICALS LIMITED.
Project Name : SINGLE POINT MOORING FACILITY(SMP) PROJECT.

Reported Date : 21-OCT-14

Monthly Report : 8 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1043.570957.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
648.9200648.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20120/012/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
58.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks