Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CAPACITY AUGMENTATION OF KOTA PIYALA SECTION OF MMBPL PIPELINE.

Reported Date : 24-FEB-14

Monthly Report : 12 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
152.890152.89

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
108.2818.61.65128.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20130/07/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7435

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project has been completed. Pipeline and pumping stations commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks