Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : CHENNAI PETROLEUM CORPORATION LIMITED.
Project Name : MOUNDED BULLET PROJECT AT CPCL.

Reported Date : 30-JUN-16

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 5 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 58 / 0 / 58

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2790279

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
142.28048.58190.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
690

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-16100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone