Reported Date :
07-NOV-19
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
9
/
2019
|
Cost Overrun (%)- 133.5
|
Time Overrun (Months)-
58
|
Total/Pending/Completed Milestone -
40
/
0
/
40
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
As of 31.8.2019, laying of 168.45 km Uran Chakan Shikrapur Pipeline has been completed.Pre-commissioning safety audit by OISD completed by 13.09.2019 and observations report given by OISD vide letter dated 23.09.19. OISD compliance works are under progress and OISD compliance report is required by PESO for sanctioning commissioning approval. Once the approval is obtained from the statutory authorities, UCSPL will be commissioned with LPG. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |