Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : URAN CHAKAN SHIKRAPUR LPG PIPELINE.

Reported Date : 07-NOV-19

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2019

Cost Overrun (%)-   133.5

Time Overrun (Months)-    58

Total/Pending/Completed Milestone - 40 / 0 / 40

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
309.81723.4723.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
645.1258.338.81712.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20148/20198/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3939

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

As of 31.8.2019, laying of 168.45 km Uran Chakan Shikrapur Pipeline has been completed.Pre-commissioning safety audit by OISD completed by 13.09.2019 and observations report given by OISD vide letter dated 23.09.19. OISD compliance works are under progress and OISD compliance report is required by PESO for sanctioning commissioning approval. Once the approval is obtained from the statutory authorities, UCSPL will be commissioned with LPG.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone