Reported Date :
11-SEP-15
|
MOU Status :
Not Under MOU for 2015-2016
|
Monthly Report :
7
/
2015
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
N.A.
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Present status:
Financial closure of pipeline has been approved by GAIL Board.
Detailed survey works of SPPL is being taken up.
Opening of office at Bhubaneshwar is being taken up.
Request letter for extension of project schedule sent to PNGRB along with justification.
GAIL plans to execute SPPL in phases.
Action taken till date :
• Earlier in 2012 tendering for survey work cancelled. Will be done once Customers tie up done.
• Office was opened at Nagpur on 07.05.2012 but closed in Apr 2014 due to unavailability of anchor load customer in SPPL and all project activities were put on hold.
• Letters containing the details of SPPL Project were submitted to all District Collectors with a copy to concerned Chief Secretaries.
- Meeting with Chief Secretary, Govt. of Gujarat held and subsequently held with all District Collectors and Chief Secretaries of
Maharashtra,Chhattisgarh and Orissa.
- Application for NH (20 nos) & Railway (24 nos.) crossing Permissions submitted (20 Nos.)
- Application for forest crossing permissions were submitted (47.45Kms) | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |