Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : SURAT PARADIP PIPELINE PROJECT.

Reported Date : 11-SEP-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 7 / 2015

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
10281010281

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.440.051.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20150/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Present status: Financial closure of pipeline has been approved by GAIL Board. Detailed survey works of SPPL is being taken up. Opening of office at Bhubaneshwar is being taken up. Request letter for extension of project schedule sent to PNGRB along with justification. GAIL plans to execute SPPL in phases. Action taken till date : • Earlier in 2012 tendering for survey work cancelled. Will be done once Customers tie up done. • Office was opened at Nagpur on 07.05.2012 but closed in Apr 2014 due to unavailability of anchor load customer in SPPL and all project activities were put on hold. • Letters containing the details of SPPL Project were submitted to all District Collectors with a copy to concerned Chief Secretaries. - Meeting with Chief Secretary, Govt. of Gujarat held and subsequently held with all District Collectors and Chief Secretaries of Maharashtra,Chhattisgarh and Orissa. - Application for NH (20 nos) & Railway (24 nos.) crossing Permissions submitted (20 Nos.) - Application for forest crossing permissions were submitted (47.45Kms)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone