Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL INDIA LIMITED.
Project Name : PURCHASE OF 2 NOS. OF 2000 HP DRILLING RIG.

Reported Date : 04-NOV-16

Monthly Report : 9 / 2016

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2700215.66

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
172.5300172.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20128/20168/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
270251.66

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks