Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : LPG TERMINAL AT KOCHI.

Reported Date : 27-JAN-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2023

Cost Overrun (%)-   103.6

Time Overrun (Months)-    62

Total/Pending/Completed Milestone - 52 / 0 / 52

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
607.0612361236

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
590.93158.050748.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/201712/202212/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
850

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone