Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS.

Reported Date : 24-SEP-18

Monthly Report : 7 / 2018

  

   

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4124.3505725.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2798.792548.705347.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20163/20187/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
16660

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project has been completed on 29.03.2018

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks