Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ADDITIONAL DEVELOPMENT OF VASAI EAST FIELD.

Reported Date : 08-SEP-16

Monthly Report : 7 / 2016

  

   

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2476.8202476.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
673.88309.040982.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20180/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1880

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-16100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks