Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CHINCHINNADA KAKINADA JUNCTION POINT PIPE LINE.

Reported Date : 06-FEB-17

Monthly Report : 12 / 2016

  

   

Total/Pending/Completed Milestone - 11 / 0 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
419.040419.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
339.139.490378.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20170/09/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.26Completed

Monthly Status

Background Information

Brief status of Project: PMC: M/s EIL Pipeline replacement jobs in KG Basin (24”X94.13 Kms ): The laying works have been awarded to M/s KPTL Construction status : Oduru - Kakinda (20 Kms): Gas in done on 08.07.2015 Tatipaka - Oduru (55 Kms):Gas in done on 29.04.2016. Chinchinada - Tatipaka (20 Kms) : Gas in done on 03.10.2016

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks