Reported Date :
06-FEB-17
|
MOU Status :
Not Under MOU for 2015-2016
|
Monthly Report :
12
/
2016
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-4
|
Total/Pending/Completed Milestone -
11
/
0
/
11
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Brief status of Project:
PMC: M/s EIL
Pipeline replacement jobs in KG Basin (24”X94.13 Kms ): The laying works have been awarded to M/s KPTL
Construction status :
Oduru - Kakinda (20 Kms): Gas in done on 08.07.2015
Tatipaka - Oduru (55 Kms):Gas in done on 29.04.2016.
Chinchinada - Tatipaka (20 Kms) : Gas in done on 03.10.2016 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |