Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : JAIPUR-PANIPAT NAPTHA PIPELINE ALONG WITH AUGMENTATION OF KOYALI-SANGANER PRODUCT PIPELINE.

Reported Date : 06-FEB-20

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2019

Cost Overrun (%)-   0

Time Overrun (Months)-    2

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8900887

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
579.5629.72.01609.29

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20190/012/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Brief Highlights: Jaipur- Panipat Naphtha Pipeline: Commissioned on 15.1.2019. Koyali - Sanganer Pipeline augmentation: • Commissioning and Hand Over: ¿ Koyali: Station commissioned on 8.8.2019 ¿ Viramgam: 2 MLPUs commissioned. ¿ Sidhpur: Station commissioned on 15.3.2019. ¿ Kot: Station commissioned on 14.5.2019. # Project mechanically completed except for installation of one MLPU in operating area at Viramgam. Installation pending due to operational constraints at present. Major Critical Areas: NIL

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone