Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PARADIP LPG IMPORT FACILITY.

Reported Date : 11-MAY-22

Monthly Report : 4 / 2022

  

   

Total/Pending/Completed Milestone - 36 / 0 / 36

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6900690

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
624.710.57625.28

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20183/20223/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
850

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.18Completed

Monthly Status

Background Information

Project is Mechanically completed in Mar 2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks