Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DAMAN DEVELOPMENT PROJECT.

Reported Date : 10-JUN-20

Monthly Report : 3 / 2020

  

   

Total/Pending/Completed Milestone - 14 / 0 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6086.085842.315842.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4762.4222.4604784.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20193/20203/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
45.6356

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-20100Completed

Monthly Status

Background Information

PROJECT COMPLETED.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks