Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : CHENNAI PETROLEUM CORPORATION LIMITED.
Project Name : NEW CRUDE OIL PIPELINE PROJECT FROM CHENNAI PORT TO MANALI REFINERY.

Reported Date : 15-NOV-18

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2018

Cost Overrun (%)-   0

Time Overrun (Months)-    22

Total/Pending/Completed Milestone - 22 / 2 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
257.870257.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
186.7140.11.91243.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20160/09/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-18100Completed

Monthly Status

Background Information

Public area: Crude oil pipe line hydro-test completed on 29.10.18. Project Mechanically Completed on 04.10.18. OISD have been requested to conduct Pre-Commissioning Safety Audit is planned by 13 & 14.10.18 Commissioning expected by end Oct 18.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone