Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : GAMJI REDEVELOPMENT PROJECT.

Reported Date : 09-APR-19

Monthly Report : 2 / 2019

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1671.2201671.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
427.5230.327.41465.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20190/02/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project Completed on 15.02.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks