Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : NUMALIGARH REFINERY LIMITED.
Project Name : DIESEL HYDROTREATOR.

Reported Date : 05-DEC-18

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 10 / 2018

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 61 / 15 / 46

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1031.3701031.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
261.221300.55562.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20180/01/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone