Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL INDIA LIMITED.
Project Name : 50 MW 10 PERSENT WIND ENERGY POWER PROJECT.

Reported Date : 07-DEC-17

Monthly Report : 10 / 2017

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5000435

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0368.240368.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20170/010/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
73.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-17100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks