Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : 50 MW CAPACITY WIND POWER PROJECT UNDER PHASE II.

Reported Date : 30-JAN-20

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 12 / 2019

Cost Overrun (%)-   19.35

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 24 / 24 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3100370

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
17.840017.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone