Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : NAWAGAM-KOYALI PIPELINE PROJECT.

Reported Date : 15-NOV-18

Monthly Report : 9 / 2018

  

   

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
195.630187.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
168.11.725.85174.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20189/20189/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
220

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-SEP-18100Completed

Monthly Status

Background Information

Project completed on 14.09.2018

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks