Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDS.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   5.8

Time Overrun (Months)-    86

Total/Pending/Completed Milestone - 15 / 1 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3190.693375.93375.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3002.913.1817.883023.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/201812/20236/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
64.470

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2589Ongoing

Monthly Status

Background Information

Present status: Safe access works are completed at all the 4 of the NS,NX & NU and SS platforms. Removal of scaffolding at WB platform completed to enable other projects work. Balance work at 2 minor platforms SW and SI is completed. Painting works at all the 10 platforms completed. Completion of balance work at Major platform HT is completed. Out of 25 platforms, balance RTU and SCADA integration works at 19 executed platforms are completed, balance works are in progress at 6 platforms. Balance works are scheduled to be completed by 30.06.2025 Condition survey is completed at all the 10 major platforms and submitted reports to EIL for assessment study and recommendation. Post assessment study a decision can be taken for way forward to be adopted for these 10 platformsThe facilities are being executed through three packages. Package-I: • Platform specific jacket repair, Topside structural strengthening and facility revamping of 20 well head platforms (14 Major & 06 Minor topside revamp). • NOA placed to Consortium of M/s AFCONS-HALANI-TRIUNE on 29.01.2016. • Work completed at 14/20 platforms (09 major + 05 Minor). • Offshore Work could not be resumed due to non-availability of Specified Period License (SPL) in monsoon period 2021 (Oct-21 to May-22). * 14/20 platforms revamping job completed with punch points and painting job of 4/14 platforms completed Package-II: • Revamping of topside at 11 platforms, Repair of jacket structural member (above water level) at 9 platforms, under water repair of jacket at 15 platforms, Removal of Sump Caisson from 37 platforms and Removal of Fire Water pump casing from 30 platforms. • NOA placed to Consortium of M/s AFCONS-HALANI-TRIUNE Energy Services on 31.05.2016. • Under water jacket repair works completed at all 15 platforms. • Fire water casing removal completed at all 30 platforms. • Sump Caisson removal work completed at all 37 platforms. • Revamp of topside / repair of jacket structural work is completed at 13/20 platforms and One HE wellhead platform completed during the month. (SPL) got from DGS for one vessel Trinity Nissi, was mobilized to Offshore on 29.04.2022. Completed balance work at HE platform and demobilized on 18.05.2022. • Offshore Work hampered due to non-availability of Specified Period License (SPL) in monsoon period 2021 (Oct-21 to April-22). Completed balance work at HE platform and demobilized on 18.05.2022. Job was under taken only for around 15 days at HE Platform. Package-III: • Complete topside deck replacement of 10 well head platforms of MH Asset. • Package completed on 22.05.2018 Issues: • Offshore Project LEWPP progress suffered badly due to non-availability of Specified Period License (SPL) in the period October-21 to May-22. As per above order, there are additional requirements that need to be complied with immediate effect. Like, Lifeboats of 100% POB capacity on each side of the Barge are to be installed within 6 months from the date of this order. Contractors informed that the availability of such barges in market is very less. Due to which, mobilization of adequate number of barges to complete the balance work in one construction season would be a challenge. Consortium requested to extend the completion date of the contracts up to 15.05.2026. Board approved extension of completion date till 31.12.2023 to firm up the way forward.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone