Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : SIX PIPELINE REPLACEMENT PROJECT.

Reported Date : 20-JUL-18

Monthly Report : 5 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
181.02181.02181.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
174.65.05.18174.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20175/20185/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
350

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-18100Completed

Monthly Status

Background Information

All 5 segments viz. F1,F2,F3,F4 &F5, were completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks