Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : RAZE REBUILD AND REVAMP OF MARKETING DEPOT AT DOIMUKH.

Reported Date : 15-MAY-19

Monthly Report : 3 / 2019

  

   

Total/Pending/Completed Milestone - 10 / 5 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
247.520247.52

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
106.7345.4111.28163.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20190/03/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6060

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project is mechanically completed. Piping and Plant Building works completed. Non Plant Building works completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks