Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : RESITING OF TINSUKIA TERMINAL PROJECT (DIGBOI MARKETING TERMINAL PROJECT).

Reported Date : 07-DEC-17

Monthly Report : 10 / 2017

  

   

Total/Pending/Completed Milestone - 12 / 6 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1500259.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
208.9242.980251.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20140/010/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
58.750

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks