Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : CHENNAI PETROLEUM CORPORATION LIMITED.
Project Name : DHDS REVAMP FOR MEETING BS-IV DIESEL QUALITY.

Reported Date : 17-APR-18

Monthly Report : 2 / 2018

  

   

Total/Pending/Completed Milestone - 22 / 0 / 22

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
367.110367.11

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
181.7263.316.6251.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20170/02/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-FEB-18100Completed

Monthly Status

Background Information

Plant completed & commissioned on 28th Feb 18.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks