Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : PROPYLENE DERIVATIVES PETROCHEMICAL PROJECT(PDPP) AT KOCHI REFINERY.

Reported Date : 14-OCT-21

Monthly Report : 10 / 2021

  

   

Total/Pending/Completed Milestone - 20 / 20 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4588.2955755575

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4387.23989.2705376.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/201811/20199/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks