Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : ANKLESHWAR BARODA PIPELINE PROJECT.

Reported Date : 07-FEB-19

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 12 / 2018

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 22 / 0 / 22

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
199.950199.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
154.372.460156.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Construction status: - Pipeline Laying Work Complete. - Mechanical Completion -31.03.18. - Gas in done on 24.12.18 - Project Completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone