Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CAPACITY AUGMENTATION JAMNAGAR LONI PIPELINE.

Reported Date : 07-APR-22

Monthly Report : 3 / 2022

  

   

Total/Pending/Completed Milestone - 20 / 0 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
327.780220

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
194.45.7.2200.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20180/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
020

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks