Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : IRUGUR-DEVANGONTHI POL PIPELINE.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
67817321732

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
583.7631.7227.28642.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/201710/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
64.1Ongoing

Monthly Status

Background Information

1)Pipeline Laying contractor are being mobilized at site in all 3 spreads. 2)Pipeline Welding 201.9 KM 3)Pipeline Lowering 170.4 KM 4)Station Civil and Piping works are in progress. 5)Mechanical equipment erection works started in Devangonthi RT.Pipeline Laying contrator are being mobilised at site. 1)Pipeline Route Survey 219 KM 2)Pipeline Stringing 40 KM 3)Pipeline Welding 21 KM 4)Pipeline Lowering 2 KM

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks