Reported Date :
07-JAN-22
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
12
/
2021
|
Cost Overrun (%)- 18.68
|
Time Overrun (Months)-
21
|
Total/Pending/Completed Milestone -
13
/
2
/
11
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
PROJECT IS MECHANICALLY COMPLETED ON 10th MAY 2021. COMMISSIONING DELAYED DUE TO DELAY IN SIDING WORKS BY RAILWAYS | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |