Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : VVSPL CAPACITY EXPANSION AND OSTT-SS JETTY SUB SEA PIPELINE PROJECT.

Reported Date : 07-NOV-19

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2019

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 27 / 0 / 27

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4070407

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
347.929.0714.88391.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20190/09/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5959

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

- Ordering - NIL during September 19 - Manufacturing and Delivery including status of long lead items - VVSPL Capacity Expansion Project - NIL during Sept, 2019. All long lead items received at site. OSTT SS Jetty Subsea Pipeline project - NIL during Sept, 2019. All long lead items received at site. - Tendering - NIL during for Sept 19. - Construction - 1. Overall construction progress civil and composite for VDS – 100 percent, IPS1 – 100 percent, IPS2 – 100 percent, RBS – 100 percent, VBS – 100 percent, SBS – 100 percent and IPS3 SV17 – 100 percent. 2. Civil construction works completed in Visakhapatnam, IPS1, Rajahmundry, IPS2, Vijayawada, Suryapet and IPS3 SV17. 3. Mechanical, Piping, Electrical, Instrumentation works completed in all stations of IPS1, IPS2, IPS3, VDS, RBS, VBS and SBS. 4. HT power from Electricity board has been taken for IPS1, IPS2 and IPS3 and charging of panels completed. 5. All Mainline pumps received at IPS1 3 nos, IPS2 3 nos, IPS3 2 nos, Vizag 1 no, Rajahmundry 1 no, Vijayawada 1 no and Suryapet 2 nos. 6. PLC upgradation works completed for all existing stations. - Commissioning and Hand over: IPS1, IPS2 and IPS3 SV17 stations commissioned and handed over. Subsea Pipeline mechanically completed. Process stabilization is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone