- Ordering - NIL during September 19
- Manufacturing and Delivery including status of long lead items -
VVSPL Capacity Expansion Project - NIL during Sept, 2019. All long lead items received at site.
OSTT SS Jetty Subsea Pipeline project - NIL during Sept, 2019. All long lead items received at site.
- Tendering - NIL during for Sept 19.
- Construction -
1. Overall construction progress civil and composite for VDS – 100 percent, IPS1 – 100 percent, IPS2 – 100 percent, RBS – 100 percent, VBS – 100 percent, SBS – 100 percent and IPS3 SV17 – 100 percent.
2. Civil construction works completed in Visakhapatnam, IPS1, Rajahmundry, IPS2, Vijayawada, Suryapet and IPS3 SV17.
3. Mechanical, Piping, Electrical, Instrumentation works completed in all stations of IPS1, IPS2, IPS3, VDS, RBS, VBS and SBS.
4. HT power from Electricity board has been taken for IPS1, IPS2 and IPS3 and charging of panels completed.
5. All Mainline pumps received at IPS1 3 nos, IPS2 3 nos, IPS3 2 nos, Vizag 1 no, Rajahmundry 1 no, Vijayawada 1 no and Suryapet 2 nos.
6. PLC upgradation works completed for all existing stations.
- Commissioning and Hand over:
IPS1, IPS2 and IPS3 SV17 stations commissioned and handed over. Subsea Pipeline mechanically completed.
Process stabilization is in progress.
| |