Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : MDPL CAPACITY EXPANSION AND PALANPUR VADODARA PIPELINE EXTENSION.

Reported Date : 09-FEB-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 24 / 0 / 24

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
187901689

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1634.7359.5201694.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20200/010/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
230

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed