The KG-DWN-98/2 Cluster II project has completed drilling of all 26 wells including oil, gas and water injectors, with first gas achieved in 2020 and first oil in January 2024. All subsea structures including manifolds, risers and jumpers have been installed. The gas system is commissioned and the oil system is fully operational. The CPP topside has been installed but LQUP topside installation is pending due to crew clearance issues. FPSO has been commissioned and handed over to operations after successful testing. Onshore Terminal facilities at Odalarevu and Mallavaram are under final stages of commissioning with overall physical progress over 95 percent. | Execution of the project is being carried out through 05 major packages
Package-I: Hiring of Drilling Rigs, Bundle Services and Well Completion Services
• Contract for Drilling Bundle services re-awarded to Consortium of M/s Schlumberger Oil Field Eastern Limited, M/s Schlumberger Solutions Private Limited & M/s Kakinada Marine and Offshore Complex Limited on 30.03.2021. Contract for Bundle Testing Services re- awarded to M/s. Halliburton on 05.04.2021.
• Drilling for all the wells completed.
• Sch. Progress: 100% Act. Progress: 100%.
Package-II: Combined SPS + SURF Package
• NOA issued to Consortium of M/s GEUK, M/s GEVG, M/s McDermott, M/s BMD and M/s LTHE on 01.10.2018.
• Sch. Progress: 100% Act. Progress: 84.96%.
Package-III: Offshore Gas Process Platform and LQ (CPP+LQUP)
• NOA issued to Consortium of M/s Afcons Infrastructure Ltd (AFCONS), Mumbai and M/s Sapura Fabrication Sdn Bhd (SFSB), Malaysia on 10.11.2018
• Sch. Progress: 100% Act. Progress: 89.98%.
Package-IV: Hiring of FPSO (Floating Production Storage and Offloading unit)
• NOA issued to M/s. Shapoorji Pallonji Bumi Armada Godavari Pvt. Ltd. on 02.05.2019
• Sch. Progress: Plan 100%, Act. Progress: 99.71%
Package-V: Onshore Terminal
• NOA issued to M/s. Tata Projects Limited on 26.12.2018.
• Sch. Progress: 100%, Act. Progress: 90.15% |