Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : KG-DWN-98-2 CLUSTER II DEVELOPMENT PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 20 / 4 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
34012034012

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
32565.18584.1117.8733167.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20203/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
14200

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-2596.4Ongoing

Monthly Status

Background Information

The KG-DWN-98/2 Cluster II project has completed drilling of all 26 wells including oil, gas and water injectors, with first gas achieved in 2020 and first oil in January 2024. All subsea structures including manifolds, risers and jumpers have been installed. The gas system is commissioned and the oil system is fully operational. The CPP topside has been installed but LQUP topside installation is pending due to crew clearance issues. FPSO has been commissioned and handed over to operations after successful testing. Onshore Terminal facilities at Odalarevu and Mallavaram are under final stages of commissioning with overall physical progress over 95 percent.Execution of the project is being carried out through 05 major packages Package-I: Hiring of Drilling Rigs, Bundle Services and Well Completion Services • Contract for Drilling Bundle services re-awarded to Consortium of M/s Schlumberger Oil Field Eastern Limited, M/s Schlumberger Solutions Private Limited & M/s Kakinada Marine and Offshore Complex Limited on 30.03.2021. Contract for Bundle Testing Services re- awarded to M/s. Halliburton on 05.04.2021. • Drilling for all the wells completed. • Sch. Progress: 100% Act. Progress: 100%. Package-II: Combined SPS + SURF Package • NOA issued to Consortium of M/s GEUK, M/s GEVG, M/s McDermott, M/s BMD and M/s LTHE on 01.10.2018. • Sch. Progress: 100% Act. Progress: 84.96%. Package-III: Offshore Gas Process Platform and LQ (CPP+LQUP) • NOA issued to Consortium of M/s Afcons Infrastructure Ltd (AFCONS), Mumbai and M/s Sapura Fabrication Sdn Bhd (SFSB), Malaysia on 10.11.2018 • Sch. Progress: 100% Act. Progress: 89.98%. Package-IV: Hiring of FPSO (Floating Production Storage and Offloading unit) • NOA issued to M/s. Shapoorji Pallonji Bumi Armada Godavari Pvt. Ltd. on 02.05.2019 • Sch. Progress: Plan 100%, Act. Progress: 99.71% Package-V: Onshore Terminal • NOA issued to M/s. Tata Projects Limited on 26.12.2018. • Sch. Progress: 100%, Act. Progress: 90.15%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks