Reported Date :
10-JUN-20
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
2
/
2020
|
Cost Overrun (%)- 9.85
|
Time Overrun (Months)-
-10
|
Total/Pending/Completed Milestone -
5
/
0
/
5
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Brief Highlights:
• Material Procurement: All critical material available at site.
• Works: All major works awarded.
• Construction Status:
- Switchyard works at Patna: Mechanically completed.
- Mainline works: Completed
• Commissioning and Hand Over: Patna- Siwan- Motihari Section Commissioned on 15.07.2019 and Siwan- Baitalpur section commissioned on 25.02.2020. Project Completed.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |