Reported Date :
05-DEC-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
11
/
2024
|
Cost Overrun (%)- 33.98
|
Time Overrun (Months)-
75
|
Total/Pending/Completed Milestone -
5
/
0
/
5
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Construction :
Phase 1 (22.6 km) , Phase 2 (143 km) Completed.
Phase 3 (900 km) completed.
Status of remaining work is as follows:
1. IP102A to PPN Power (162.5 Km ): Pipes received. Mainline laying work yet to be awarded.
2. IP103 to CBR Refinery (Trichy to Naganpattinam : 114 km): Mainline work completed. Work for conversion of pipeline for use as NG pipeline is in progress. Work in progress in all 6 SV locations and RT location at
Nagappattinam.
3. Tiruvallur Bangalore pipeline extension (Tattanur-SV01 Section: 6.43 Km): Hydro testing completed.
4. Thiruvallur (SV-103) to Sri city Spur line (38.16 Km): 26 Km welding and 23 Km lowering completed. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |